Gere HPP - Lot 2

The Gere HPP was conceived in previous design phases as a traditional high-head scheme with a nearly horizontal, approx. 2 km long low-pressure headrace and an 800 m long buried penstock. The low-pressure headrace was designed as a tunnel with an exposed pressure line inside, being the tunnel intended also for acceding the headworks in the winter season. During the offer preparation for engineering services including tender, detail design, site supervision and commissioning, Lombardi as a member of the JV IGSL proposed a scheme modification with a 2.6 km long inclined tunnel from the powerhouse area up to the desander facilities and the Tirolean intake. The winter access function of the tunnel was maintained as in the original layout. The project was awarded to IGSL adopting this layout optimization. Drill-and-blast underground excavation was carried out from the d/s portal only. The tunnel portal is located close to the powerhouse, easily accessible and just approx. 300 m from the designated dumping area. After excavation completion, the GRP-line was installed in the tunnel from u/s to d/s. Site logistics could be dramatically simplified compared to the original project layout: the two cableways for conveyance of the excavation material to the dumping area and for penstock installation were no more needed and the project environmental impact could be further reduced. Lombardi was in charge of all conceptual and design project issues whereas our JV partner is responsible for project management and site supervision.
Country
Switzerland
Reference location
Oberwald VS
Final client
KWOG Kreftwerke Obergoms Ltd.
Is Consortium
False
Start of works date
12/1/2017
End of works date
12/31/2020
Start of services date
12/1/2016
End of services date
12/31/2021
Services
Civil designs; Construction supervision; Preliminary studies