St. Gotthard Road Pass - N2P
Page Content
The project includes the rehabilitation of the Gotthard pass road. Lombardi Ltd. is responsible for the electromechanical and safety equipment.
The project is divided into three distinct areas:
- Schöllenen (Göschenen to Andermatt)
- Gotthard north (Andermatt to pass height)
- Gotthard south (Pass height to Airolo).
The road stretches comprise both open-sky road segments as well as various tunnels and avalanche protection galleries.
Important rehabilitation works are required in particular for the single-tube tunnel Costoni di Fieud which will be equipped with a safety tunnel.
Reference location
Göschenen / Airolo
Final client
Federal Roads Office (FEDRO), Zofingen
Start of works date
10/1/2012
End of works date
12/31/2021
Start of services date
10/1/2012
End of services date
12/31/2021
Services
Electromechanical designs; Construction supervision