All references

Rollup Image
  
  
  
  
Content Type
  
  
Page Content
  
BMVIT ExpertsReferences_264Road tunnelsConsultancyLombardi Reference PageLombardi Reference Page
The Austrian road safety legislation requires formal approval of new tunnels as well as tunnel rehabilitation projects by the ministry of transport, infrastructure and technology. Approval is required for the basic design (STSG §7) as well as the final design prior to commissioning (STSG §8). In this regard and on behalf of the ministry, Lombardi SA has been mandated to establish safety expertises regarding the following tunnel objects: - Tunnel chain Klaus - Kaisermühlen Tunnel - Liefering Tunnel
Austria
Agua Negra TunnelReferences_187Road tunnelsPreliminary studies; Civil designs; Electromechanical designs; Owner's supportLombardi Reference PageLombardi Reference Page
The Agua Negra tunnel is the main component of the "Bioceanic Corridor", an international project aimed to set an efficient roadway crossing through the Andes Cordillera, connecting Porto Coquimbo (Chile) to Porto Alegre (Brazil). The project includes the construction of a 13.9 km long twin tunnel, linking the two portals at 4'080 m a.s.l. (Argentina) and 3'605 m a.s.l. (Chile). The tunnel is provided with cross passages every 250 m, two ventilation caverns (one provided with a vertical ventilation shaft of 500 m, the other with a 4.5 km long ventilation tunnel). The project includes also the ramps and the control building. The cross section is horse-shoe shaped and the carriage way is two lane wide, with a free section 7.50 m wide and 4.80 m high. There are walk ways on both sides. According to the concept for a longitudinal ventilation, the tunnel is not provided with an intermediate slab. The construction concept is to excavate the tunnel from both portals, with two contemporary and independent excavation faces each. The excavation will be drill & blast in order to assure the maximum adaptability to the geological conditions. Particular aspects of the project are the high elevation of the portals, the distance to the nearest urban center (>200 km), the extreme meteorological conditions in terms of wind and thermal excursion and the high seismic risk. Lombardi is responsible of the new conceptual study, the preliminary project and the technical tender documentations for the underground and external civil works as well as for the electromechanical equipment.
Argentine/Chile
New Albula Tunnel II - Lot 105, Consolidation Raibler CornieuleReferences_1842Railway tunnelsSpecial studies; Construction supervisionLombardi Reference PageLombardi Reference Page
The 5‘864 m long Albula Tunnel (I) is situated on the railway line Chur-Thusis-St. Moritz and was put into operation in 1903. The new Albula Tunnel II is being constructed parallel to the existing Albula Tunnel with an axial distance of 30 m. When constructing the first Albula Tunnel I, the aquiferous zone of the so-called Raibler-Formation (cell dolomite rock) already revealed to be a geologically difficult zone. In 2013, starting from a specially excavated cavern connected to the existing tunnel, exploration drillings have been done in the whole Raibler-Formation zone in order to develop a more accurate geological model. The cavern, situated in the axis of the Albula Tunnel II, is only accessible through a cross passage from the Albula Tunnel I. Following the drillings results, the Raibler-Formation can be subdivided in three different geological sectors. The sector denominated III is a fault zone of silty fine sand (swimming Raibler-Formation) with a water pressure of approximately 5 bar. For safety reason the sector III will be excavated with the freezing method. Before starting the excavation the ice casing will have to be built. This will perform a temporary support against rock and groundwater pressure and furthermore ensure the sector’s impermeability during construction time. Apart from the drillings for the construction of the ice casing, control drillings to monitor the ice casing’s impermeability and injection and drainage drillings to reduce the amount of water, will be necessary. The ice casing will be retained until the termination of the excavation and inner lining in sector III.
Switzerland
Bridge “Garibaldi” Island La MaddalenaReferences_3746Various traffic infrastructuresCivil designsLombardi Reference PageLombardi Reference Page
The new Bridge “Garibaldi” that connects the Island La Maddalena and Island Caprera (Province of Olbia) has been achieved in the work planned for the extraordinary meeting of the G8 in July 2009 based on original Italian presidency, then held in L'Aquila. The project involves the removal of the bridge temporary Bailey-type and the creation of a new road and pedestrian bridge linking the Island of La Maddalena with Island of Caprera. The longitudinal profile of the new deck is curved circular shape. The shell geometry characterizes the circular structural pattern of the bridge, so that curved surfaces with a minimum thickness and of variable width, depending on aesthetic requirements, generate a significant spatial variability of the structure. This structural design has been determined in accordance with both functional and aesthetic impact constraints, given also the high quality environment and landscape of the site. The bridge is developed above the sea along a straight axis with central span 52 m, with a maximum height of about 5.6 m above the water level. The cross section of the bridge is 10 m wide, the space to vehicular traffic is 6 m. On the sides there are two protected pedestrian and cycle paths each of a width 1.8 m. For the extraordinary time demands given by the construction company the bridge was completed in just 4 months of work.
Italy
Design of complex tunnel portalsReferences_4717Various underground structuresCivil designs; Special studiesLombardi Reference PageLombardi Reference Page
Advanced numerical analyses of tunnel portals are needed in case of several complex design conditions. Lombardi Ltd. provides studies in this field, using both commercial 2D and 3D numerical software as well as in-house developed softwares. Lombardi has gained specific experience by dealing with design cases of considerable complexity. A study of particular relevance was the analysis of the portal of three tunnels located within a large slope of cohesionless soil. In this case, the close to limit equilibrium condition of the slope itself, as well as the diagonal entrance direction of the tunnels, called for 3D numerical modelling. The effects of the excavations on the slope stability were evaluated and the tunnel lining was designed, taking into account the staggered excavation start of the tunnels. Additionally, due to the high seismicity of the site area, seismic analyses were performed. For the design of portal supports, a particular case to be studied was the entrance of a double tube road tunnel through a railway embankment. Because of the diagonal entrance direction of the tunnels, the use of permanent soil anchors in the design of the retaining structure would have interfered with the nearby tube, and was therefore not allowed. Therefore, the final design provided a support structure to withstand the long term earth pressure. The complex portal geometry required 3D numerical modelling. Furthermore, considering the tunnels passing underneath an existing railway line, possible settlements at the railtrack level had to be verified.
Various countries
Preliminary design of TBMReferences_4931Various underground structuresPreliminary studies; Special studiesLombardi Reference PageLombardi Reference Page
The selection of the excavation method is a key aspect for the design of tunnels. The mechanized excavation by means of Tunnel Boring Machines (TBM) is possible and convenient only in specific geomechanical conditions. The preliminary TBM design becomes therefore relevant in order to define the main features of the TBM, determining the feasibility of this methodology, and considering schedules and costs. The main characteristics of the TBM, i.e. advancement thrust, cutter head torque, shield geometry, cutter head properties and power of the hydraulic equipment, can be established by studying the geological framework and carrying out a proper geomechanical analysis. Other relevant aspects as the drilling machinery for the grouting works and geological investigations as well as the equipment required for the backfilling of the annular void can also be defined at this stage. In specific geomechanical conditions, advanced calculations (typically 3D) could be required. The performance of such models must take into account the interaction between mechanized excavation and the geological setting. Lombardi Ltd. has been actively involved in this engineering framework, carrying out successfully the preliminary TBM design regarding multiple underground works: highway, railway and hydraulic tunnels, rocky and soil ground, with high overburden or in urban areas.
Various countries
ENEL - PH Los CóndoresReferences_5507Hydroelectric plantsCivil designs; Consultancy; Owner's support; Special studiesLombardi Reference PageLombardi Reference Page
Los Cóndores is a 150 MW HPP, including a 12 km long headrace tunnel (4.6m diam, excavated by D&B and a DS hard rock TBM), a 120 m high surge shaft (6m diam), a 480 m high pressure shaft (2.6m diam), both being excavated using a raise borer machine RBM, and a 1.6 km long subhorizontal pressure tunnel leading to an underground powerhouse accommodating 2 Pelton units. The region is volcanic, with several active volcanoes in the recent geological eras. Maule Laguna volcanic complex is one of the major and the geological formation are essentially dacitic and rhyolitic lava field with rich tuff and volcanic breccia presence in subhorizonal sedimentation and several lava and basalt domes and dikes crossing these formations. Excavation of the upper waterway (HRT) is foreseen in two phases through a central adit by TBM, in order to shorten the time for accessing and execute the vertical works. During the excavation of the HRT lower reach, the TBM got stuck in a cohesionless material, likely the seat of a paleo-basin (syncline) or a paleo-canal within the lava and breccia banks. The services targeted the understanding of the situation, definition of the operations required for the TBM to be safely unlocked from the jammed conditions and option for realizing a bypass around the TBM in case no success was provided by other means. Because of the significant modification of the working program, the evaluation was required of the options for realizing the upper reach of the HRT by other mechanized means (second TBM) or other excavation method, given the logistic conditions at site. Possible optimization of vertical works, in terms of efficiency and realization concept was also part of the required services; in particular, a preliminary study considering 5 alternatives of the scheme combined with different excavation methods options (D&B and/or RBM) were carried out, in order to analyze the possibility to disassociate the construction of the vertical works from the TBM advance and to better manage the geological and construction risks associated with vertical works construction.
Chile
Turin-Ceres - Connection of the line with the RFI network - EquipmentReferences_2529Railway tunnelsElectromechanical designsLombardi Reference PageLombardi Reference Page
The connection of the Turin-Ceres railway (Gruppo Torinese Trasporti) with the Turin railway network (Rete Ferroviaria Italiana) represents important underground works of approximately 4.2 km including the realization of a new twin-track tunnel along Largo Grosseto, the completion of Rebaudengo Station and the adaption of an existing twin-track tunnel section. In addition to the structural design, Lombardi has developed the detailed design of the necessary electromechanical equipment to ensure the safety of users and the functionality of the railway’s operation. The design of Grosseto Station has been developed using Building Information Modelling (BIM) which allowed an efficient interaction between the different design disciplines, obtaining a high-quality result. The electromechanical system, designed with respect to the safety requirements of the Ministerial Decree 28.10.2005 “Safety of railway tunnels”, includes the medium and low voltage power supply, the normal and emergency lighting system, a complex ventilation and fumes control system for the underground stations, the pressurization system of the emergency exits, the fire detection system, the water distribution networks for the hydrants and the automatic high pressure sprinkler extinguishing system, the ventilation and air-conditioning of the technical rooms, the video surveillance as well as the intrusion protection and monitoring systems.
Italy
1 - 8Next